Meeting Time: October 17, 2018 at 7:00pm EDT
Note: The online Request to Speak window has expired.
The online Comment window has expired

Agenda Item

7. #R6824 Temp. Reso. #R6824 approving a piggyback agreement with Wharton-Smith, Inc., and related expenditure in an amount of $1,776,607, with a contingency for unforeseen conditions associated with the project in an amount of $100,000, for a total contract price not-to-exceed $1,876,607, for the provision of Construction Manager At Risk Construction Services for the Reclaimed Water Pipeline Project Phase 1A, utilizing the City of Clearwater Agreement for Construction Manager At Risk Services Continuing Contracts, dated August 9, 2016. (Utilities Director Jody Kirkman and Procurement Director Alicia Ayum)